Returns the number of workdays between a start date and an end date. Holidays can be deducted.
開始日と終了日 間の営業日数を返します。祝日は除くことができます。
NETWORKDAYS(StartDate; EndDate; Holidays)
NETWORKDAYS(開始日; 終了日; 祝日)
StartDate is the date from when the calculation is carried out. If the start date is a workday, the day is included in the calculation.
開始日 は、そこから計算を実行する日付です。開始日が営業日の場合は、計算に含まれます。
EndDate is the date up until when the calculation is carried out. If the end date is a workday, the day is included in the calculation.
終了日 は、そこまで計算を実行する日付です。終了日が営業日の場合は、計算に含まれます。
Holidays is an optional list of holidays. These are non-working days. Enter a cell range in which the holidays are listed individually.
祝日 は祝日のオプションリストです。祝日は休業日です。祝日が個々に一覧表示されているセル範囲を入力します。
How many workdays fall between 2001-12-15 and 2002-01-15? The start date is located in C3 and the end date in D3. Cells F3 to J3 contain the following Christmas and New Year holidays: "2001-12-24", "2001-12-25", "2001-12-26", "2001-12-31", "2002-01-01".
2001 年 12 月 15 日と 2002 年 1 月 15 日の間には営業日が何日あるかを求めます。開始日は C3、終了日は D3 にあります。セル F3 から J3 には、「2001-12-24」、「2001-12-25」、「2001-12-26」、「2001-12-31」、「2002-01-01」のクリスマスと新年休暇が含まれています。
=NETWORKDAYS(C3;D3;F3:J3) returns 17 workdays.